Council members and business leaders tour bridge construction in West
Bottoms Industrial District
Councilmembers in the
second district got a first-hand look
of construction in the West Bottoms Industrial District by touring the
bridges
at 12th
Street
and Beardsley
Road.
Councilwoman Bonnie Sue Cooper, 2nd
District-at-Large, and
Councilman John Fairfield, 2nd District, were
joined by Tom Roberts
of the Central Industrial District, and Darby Trotter of the Kansas
City
Industrial Council on the morning of July 27 and toured two of the many
capital
improvement projects scheduled for that area.
Construction on the 12th
Street Viaduct Bridge
began in November 2004. This bridge rehabilitation project is being
conducted in
three phases. Phase I, which was completed in February 2006, involved
work to restore
the viaduct’s substructure from the west approach. The
project is currently in
Phase II, which involves refurbishing the middle deck, and is scheduled
to be
complete in October 2006. The third and final phase of construction
involves
rehabilitation work on the bridge deck, as well as repairing the
eastern
substructure. The upper deck will remain open to traffic with only
partial
closures. The entire bridge is scheduled to be complete in July 2008.
The
construction on Beardsley Road
involves completely
rebuilding 640 feet of the bridge, restoring and reconstructing the
retaining
wall structure, as well as replacing 1,160 feet of roadway located
between 12th
Street
and 17th
Street.
The project began in December 2005 and is on schedule to be complete in
August
2007.
|